Willowridge levee raised, pump station under construction
As part of St. Charles Parish’s outer levee system, work continues on the Willowridge project. […]
As part of St. Charles Parish’s outer levee system, work continues on the Willowridge project. […]
Work has begun on the second phase of the Willowridge levee and $7.4 million allocated for the third phase of the project. […]
Residents living in the Willowdale and Willowridge subdivisions in Luling will be without power from 9 a.m. until 1 p.m. on Wednesday, May 21. […]
A groundbreaking for the Willowridge reach of the St. Charles Parish West Bank Hurricane Protection Levee is scheduled for 1 p.m. Jan. 22 at the end of Lafayette Drive in Luling. […]
Despite the fact that four of the six construction bids for the first phase of the Willowridge Levee were disqualified, the parish will still get a bargain if a contract with Southern Delta Construction, LLC is approved by the St. Charles Parish Council. […]
Several construction bids for the first phase of the Willowridge Levee in Luling came in much lower than expected on Tuesday, including two bids that were around 40 percent lower than cost estimates for the project. […]
A decades-long wait is over after the St. Charles Parish Council officially asked the state for permission to go out for bids on the first phase of the Willowridge levee. […]
A federal judge has ruled in St. Charles Parish’s favor regarding a conservation easement that has held up construction of the Willowridge levee in Luling. […]
St. Charles Parish officials are hopeful that a federal court will rule in their favor in the next few weeks regarding a conservation easement that has held up construction of the Willowridge levee in Luling. […]