Pumping station upgrades improving West Bank drainage
![]() |
| Courtesy Photo |
An "after" picture of the Boutte pumping station. |
In Luling, the Lakewood station has enjoyed an upgrade with the installation of automatic bar screen cleaners. The project, awarded by the Parish Council to Sealevel Construction Inc. in June, has reached substantial completion. The $1.29 million improvements allow the station to operate at its maximum capacity of 68,000 gallons per minute during heavy rain events. The station drains the Lakewood subdivision and parts of Mimosa Park.
A Hazard Mitigation Grant through the Federal Emergency Management Agency funded the project. According to the 2010 Census, Luling has more residents than any other town in St. Charles Parish, with 12,119 people.
In Boutte (population 3,075), the pump station located at the end of Turner Lane is looking more like its counterparts around the parish with the installation of a fence around the station and concrete slab meant for an emergency generator. The Boutte station’s two pumps were completely replaced as well. Capacity now equals 53,000-gallons-per-minute, almost double the previous capacity of 34,000-gallons-per-minute.
The Parish Council awarded low bidder BLD Services LLC the construction contract for the station in September in the amount of $862,103. The improvements also included upgrades to the station’s failing deck and foundation, as well as the installation of a more adequate access road for regular maintenance.
Boutte pump station helps drain residential areas directly to the west of Paul Maillard Road between the area’s two railroad tracks.
“Out of all the improvements made at pumping stations in 2010, the work at Boutte is probably the most substantial, from a before and after standpoint,” Public Works Director Sam Scholle said. “We’re able now to really ensure proper maintenance for that particular station.”
In Paradis, a very visible automatic bar screen cleaner installation to the south of Highway 90 is having a big impact on drainage in the area.
Motorists going to and from the town of 1,298 can easily spot the blue cleaners and new deck attached to the workhorse station, with a capacity of 39,000-gallons-per-minute. Sealevel Construction Inc. completed the work recently at a cost of $843,253 after final change orders. Funding assistance in the amount of $750,000 came from a FEMA Hazard Mitigation Grant.
St. Charles Parish is home to 50 pumping stations that help drain the majority of the parish’s over 50 miles of canals and ditches.
Subscribe Today and Save!!!
Buy a subscription to St. Charles Herald Guide Newspaper AND get the digital edition delivered to your inbox ABSOLUTELY FREE!St. Charles Herald Guide is the complete local news in St. Charles Parish, Louisiana.
Get your local news, sports and information from the Parish's award winning paper.
St. Charles Herald Guide has what you need.
Featured Articles
St. Charles Parish plans to go out for construction bids next month on the first...
Parish President V.J. St. Pierre, along with eight other parish presidents and...
Two juveniles and a 25-year-old man have been arrested in connection with two...
Most graduating seniors do not come close to scoring a 27 on the ACT test, but...
Brazen burglars have broken into seven Luling homes in less than two weeks, making...
The Port of South Louisiana will soon see a change in leadership after Joel T....
featured merchant

Trio charged with arson in 3 Montz fires - 786 views
Two juveniles and a 25-year-old man have been arrested in connection with two separate Friday fires in Montz – one of which destroyed a home.